Project Timeline

What’s been done so far in the Peak District, what is coming up and what will happen if the project is taken forward.

 Autumn 2014

Three sections of overhead lines in the Peak District National Park were identified as having a significant landscape and visual impact. One of the sections runs from a sealing end compound near the eastern entrance of the Woodhead Tunnel eastwards along the River Don Valley. The other two sections start at the head of the upper Longdendale Valley where the line emerges west of the Woodhead Tunnel and run down the valley along a number of reservoirs up to Tintwistle.

Winter 2014 – Autumn 2015

National Grid and independent landscape consultants undertook further technical work and considered the detailed input from local stakeholders in the Peak District. This enabled the project’s Stakeholder Advisory Group to prioritise the section of transmission line in and around the village of Dunford Bridge in September 2015.

Spring 2015

National Grid working with local partners established a Stakeholder Reference Group. The following organisations regularly attend these technical meetings:

  • Barnsley Metropolitan Borough Council
  • Dunford Parish Council
  • Natural England
  • Peak District National Park Authority
  • Trans Pennine Trail

Winter 2015 – Summer 2016

National Grid undertook environmental, archaeological, geotechnical, transport and ecology surveys in the Peak District National Park and engaged with technical stakeholders and members of the local community.

Autumn – Winter 2016

The VIP project’s Stakeholder Advisory Group reviewed the results of the environmental and engineering surveys, the stakeholder feedback and National Grid’s preferred options.  The Group recommended that the project should proceed to construction by reviewing this information and the progress of the project using the guiding principles of the VIP policy.

2017 – 2018

National Grid will continue with detailed ecological and environmental work and discussions and investigations into the appropriate underground solutions for the project.  It is currently envisaged that a planning application for the sealing end compound will be ready to submit in early 2018.

2019 – 2021

Subject to planning approval, on-site works will commence in spring 2019 and take up to two and a half years to complete (including the removal of the existing line).